Grab an Italian masterpiece for less
House of Lords
Published May 8, 2007
Melville Dundas Ltd and Others v George Wimpey UK Ltd and Others
Before Lord Hoffmann, Lord Hope of Craighead, Lord Walker of Gestingthorpe,
Lord Mance and Lord Neuberger of Abbotsbury
Speeches April 25, 2007
A provision that a party to a construction contract could not, unless he had given notice of intention to do so, withhold payment after the final date for payment of a sum due under the contract, did not apply to a lawful ground for withholding payment, such as the contractor going into receivership, when it was not possible for notice to have been given within the statutory time frame.
The House of Lords so held, Lord Mance and Lord Neuberger dissenting, when
allowing an appeal by the defender employer, George Wimpey UK Ltd, and the
third party, Norwich Union Insurance Ltd, from an interlocutor of the Extra
Division of the Inner House of the Court of Session (Lord Nimmo Smith, Lord
Mackay of Drumadoon and Lord Maclean) (2006 SLT 95) allowing a reclaiming
motion by the pursuer contractor, Melville Dundas Ltd, and its receivers,
Colin Peter Dempster and Thomas Merchant Burton, from the interlocutor of
the Lord Ordinary (Lord Clarke) (2005 SLT 24) that the pursuers were not
entitled to claim payment of £396,630 allegedly due under a construction
contract.
Mr Robert Akenhead, QC and Mr Sean Smith, of the Scots Bar,
for Wimpey; Mr Robert Howie, QC and Mr Jonathan Lake, both
of the Scots Bar, for Melville Dundas.
LORD HOFFMANN said that the contract was for the construction of a housing development in Whitecraigs, Glasgow, for a total sum of £7,088,270.
The contract incorporated the conditions of JCT Standard Form of Building Contract with Contractor’s Design (1998 edition) which provided for monthly applications for interim payments, and the final date for payment of the amount due in an interim payment was 14 days after receipt by the employer of the application.
On May 2, 2003 the contractor applied for an interim payment of £396,630 and the final date for payment was May 16. The employer did not pay on that date and on May 22 administrative receivers of the contractor were appointed by its bank.
Clause 27.3.4 of the contract provided that if the contractor had an administrative receiver appointed, the employer might determine the employment of the contractor. The employer exercised that right on May 30, 2003.
That brought into effect clause 27.6.5.1 which stated that the provisions of the contract which required any further payment to the contractor should not apply, but that clause should not be construed so as to prevent the enforcement by the contractor of any rights under the contract in respect of amounts properly due to be paid by the employer to the contractor which the employer had unreasonably not paid and which, where clause 27.3.4 applied, had accrued 28 days or more before the date when under clause 27.3.4 the employer could first give notice to determine the contractor’s employment.
His Lordship said that “require any further payment” meant “require the employer to pay any more money”.
The next question was whether the effect of clause 27.6.5.1 was invalidated by the Housing Grants, Construction and Regeneration Act 1996.
The effect of clause 27.6.5.1 was to disentitle a contractor from being paid an instalment to which, until determination under clause 27.3.4, he would have been entitled under the contract. Was there anything in the 1996 Act which said that the contract could not so provide?
It was apparent from sections 109 to 110(1) of the 1996 Act that their object was to introduce clarity and certainty as to the terms of a construction contract rather than to dictate to the industry what those terms should be.
The only substantive requirement was that the contractor should be entitled to payment by instalments and that there should be an adequate mechanism for determining what he was entitled to be paid and when. The statute went no further.
Instalment payments were in their nature provisional liabilities. They were to provide the cash flow for the contractor or subcontractor to enable him to perform his duties under the contract.
But when the contractor’s employment had been determined in consequence of the appointment of a receiver, two consequences followed: first the contractor had no longer any duties to perform; second, the liability to make an interim payment was no longer provisional.
While the employer retained the money, he could set it off against his cross-claim for noncompletion against the contractor. In practice, where the contractor had become insolvent, the employer would have a cross-claim for damages which exceeded the contractor’s claim for unpaid work.
On the other hand, once the employer had paid the money it was gone. It was swept up by the bank’s floating charge and the employer would have to prove in the liquidation for his cross-claim.
Upon insolvency, liability to make an interim payment therefore became a matter which related not to cash flow but to the substantive rights of the employer on the one hand and the contractor’s secured or unsecured creditors on the other.
A provision such as clause 27.6.5.1, which gave the employer a limited right to retain funds by way of security for his cross-claims, seemed a reasonable compromise between discouraging employers from retaining interim payments against the possibility that a contractor who was performing the contract might become insolvent at some future date, which might well be self-fulfilling, and allowing the interim payment system to be used for a purpose for which it was never intended, namely, to improve the position of an insolvent contractor’s secured or unsecured creditors against the employer.
The contractor also relied on section 111(1) of the 1996 Act and said that the employer was not entitled to withhold the interim payment because it did not serve a notice earlier than the prescribed period, which the JCT conditions fixed at five days before the final date for payment on May 16, 2003.
It would not have been possible for the employer to serve such a notice by May 11. The earliest they could have been known that they were entitled to withhold the interim payment was when the receivers were appointed on May 22. To make clause 27.6.5.1 subject to the notice requirement of section 111(1) would be in effect to write it out of the contract.
It would be absurd to impute to Parliament an intention to nullify clauses like 27.6.5.1, not by express provision in the statute, but by the device of providing a notice requirement with which the employer could never comply. Section 111(1) had to be construed in a way which was compatible with the operation of clause 27.6.5.1.
His Lordship would say lex non cogit ad impossibilia and that on that ground section 111(1) should be construed as not applying to a lawful ground for withholding payment of which it was in the nature of things not possible for notice to have been given within the statutory time frame.
That might not be particularly elegant, but the alternative was to hold that the parties’ substantive freedom of contract had been indirectly curtailed by a mere piece of machinery, the operation of which would serve no practical purpose. That was even less attractive.
Lord Hope delivered a concurring speech and Lord Walker agreed with Lord Hoffmann. Lord Mance and Lord Neuberger delivered dissenting speeches.
Solicitors: MacRoberts, Glasgow; Maclay Murray & Spens, Edinburgh.
Articles from our sister site WSJ.com:
You may be asked to subscribe to read certain articles
Industry sectors news at a glance. Interactive heatmap, video and podcast
Everything the Business Traveller needs to know to make a better trip
Get ready for the winter sports season, with our resort guides and snow reports
We are backing British business, what is the confidence of the nation and what businesses are succeeding?
Growing demand for energy, oil that is harder to reach and the rise of carbon dioxide emissions. We examine the energy challenge
With rail travel in Europe on the rise, we review the benefits of travelling by train
Enjoy further reading from Travel to Fashion, Business to Sport, discover more
Shortcuts to help you find sections and articles
1998
£47,955
12 months for the price of 11 and a 5% discount.
Offer ends 31/11/09
Check your free Experian credit report before applying
Car Insurance
to £60K + bonus (OTE £90k)
Lord Search & Selection
Location Flexible
PwC’s Consulting practice helps businesses of all shapes
and sizes work smarter and grow faster.
£85k
CPA
Highly Competitve
Specsavers
Whiteley, near Southampton
Moments from Battersea Park.
For sale with Winkworth
Find out about shared ownership.
See your free Experian credit report beforehand
Book now & save over £100pp.
11 cool resorts, lowest prices... Early Booking offers 15 Nov.
20% off selected Azores holidays taken in October with Sunvil Discovery
Get covered on your travels with a superb range of policies at great prices. Visit InsureandGo.com
World Class Golf, Spa and preferential Beach Club. Private estate overlooking West Coast
Villas from £275 per night inclusive of Golf
Contact our advertising team for advertising and sponsorship in Times Online, The Times and The Sunday Times, or place your advertisement.
Times Online Services: Dating | Jobs | Property Search | Used Cars | Holidays | Births, Marriages, Deaths | Subscriptions | E-paper
News International associated websites: Globrix Property Search | Milkround
Copyright 2009 Times Newspapers Ltd.
This service is provided on Times Newspapers' standard Terms and Conditions. Please read our Privacy Policy.To inquire about a licence to reproduce material from Times Online, The Times or The Sunday Times, click here.This website is published by a member of the News International Group. News International Limited, 1 Virginia St, London E98 1XY, is the holding company for the News International group and is registered in England No 81701. VAT number GB 243 8054 69.
Your Comments
Order By: